Solar, wind and battery projects near Peterhead (AB42)
25 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of AB42 (Aberdeenshire): 3 are waiting for a planning decision, 13 approved but not yet running, 5 operational. The largest live scheme is Greystone, Blackhills (500 MW battery storage, application submitted on 4 July 2025, no decision recorded), 4.0 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Hywind Scotland Pilot Park (Hywind 2) Demonstrator (30 MW, operational), 27.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of AB42
Projects of 1 MW and more (21)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Netherton, Langside Roadbattery storage | battery storage | 400 | application submittedupdated Oct 2025 | Aug 2025 | — | Oct 2025 | Aberdeenshire | 0.8 |
| Flushing, Longsidebattery storage | battery storage | 400 | application submittedupdated Oct 2025 | Jul 2025 | — | Oct 2025 | Aberdeenshire | 1.7 |
| Greystone, Blackhillsbattery storage | battery storage | 500 | application submittedupdated Oct 2025 | Jul 2025 | — | Oct 2025 | Aberdeenshire | 4.0 |
| Hillhead Of Gask, Longhavensolar farm | solar farm | 14.2 | under constructionupdated Feb 2026 | Jan 2022 | granted Apr 2022 | Feb 2026 | Aberdeenshire | 4.8 |
| Hill of Bracowind farm | wind farm | 20 | application withdrawnupdated Sep 2013 | Feb 2013 | — | Sep 2013 | Aberdeenshire | 5.3 |
| Hywind 2battery storage | battery storage | 1 | operationalupdated Nov 2018 | — | — | Nov 2018 | Aberdeenshire | 5.5 |
| Bruxiehall Farmsolar farm | solar farm | 2 | under constructionupdated Jan 2019 | Sep 2015 | granted Nov 2015 | Jan 2019 | Aberdeenshire | 5.9 |
| Salamander Offshore Wind Farm Battery Storage and Onshore Connectionbattery storage | battery storage | 180 | approved, not builtupdated Nov 2025 | Aug 2024 | granted Oct 2025 | Nov 2025 | Aberdeenshire | 6.6 |
| Fraserburgh Road - Kirkton Solar PV Farm & Energy Storage Facilitysolar farm | solar farm | 50 | approved, not builtupdated Mar 2023 | Feb 2021 | granted Dec 2022 | Mar 2023 | Aberdeenshire | 7.2 |
| Fraserburgh Road - Kirkton Solar PV Farm & Energy Storage Facilitybattery storage | battery storage | 20 | approved, not builtupdated Mar 2023 | Feb 2021 | granted Dec 2022 | Mar 2023 | Aberdeenshire | 7.2 |
| Upper Kinknockie Wind Farmwind farm | wind farm | 1.5 | application withdrawnupdated May 2012 | Nov 2011 | — | May 2012 | Aberdeenshire | 7.3 |
| St Fergus Renewable Energy Parksolar farm | solar farm | 5 | under constructionupdated Feb 2023 | Dec 2019 | granted Jul 2021 | Feb 2023 | Aberdeenshire | 7.8 |
| St Fergus Renewable Energy Parkwind farm | wind farm | 3 | under constructionupdated Feb 2023 | Dec 2019 | granted Jul 2021 | Feb 2023 | Aberdeenshire | 7.8 |
| St Fergus Moss Wind Farmwind farm | wind farm | 6 | operationalupdated Mar 2013 | Jun 2010 | granted Feb 2012 | Mar 2013 | Aberdeenshire | 7.9 |
| West Knock Wind Clusterwind farm | wind farm | 2.4 | operationalupdated Oct 2013 | Jul 2009 | granted Apr 2011 | Oct 2013 | Aberdeenshire | 8.0 |
| Yonderton Farmwind farm | wind farm | 1 | operationalupdated Jan 2015 | May 2010 | granted Jul 2010 | Jan 2015 | Aberdeenshire | 8.3 |
| Yonderton Farmwind turbine | wind turbine | 1 | refusedupdated Dec 2012 | Sep 2011 | refused Aug 2012 | Dec 2012 | Aberdeenshire | 8.4 |
| South of Greenwellheadssolar farm | solar farm | 5 | abandonedupdated Jul 2020 | Sep 2015 | granted Oct 2015 | Jul 2020 | Aberdeenshire | 8.9 |
| Land at Overside and Greenwellheads Farmswind farm | wind farm | 9.2 | operationalupdated Dec 2013 | Mar 2011 | granted Sep 2011 | Dec 2013 | Aberdeenshire | 9.0 |
| Greenside Extensionwind farm | wind farm | 7 | approved, not builtupdated May 2025 | Mar 2024 | granted Mar 2025 | May 2025 | Aberdeenshire | 9.5 |
| Bilbo Solar Farmsolar farm | solar farm | 36.6 | under constructionupdated Oct 2024 | Jun 2019 | granted Nov 2019 | Oct 2024 | Aberdeenshire | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (4)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Middleton Of Rorasolar farm | solar farm | — | approved, not builtupdated Aug 2025 | Mar 2025 | granted Jul 2025 | Aug 2025 | Aberdeenshire | 4.1 |
| Hillhead Of Gask, Longhaven -Battery Storagebattery storage | battery storage | — | under constructionupdated Feb 2026 | Jan 2022 | granted Apr 2022 | Feb 2026 | Aberdeenshire | 4.8 |
| Laeso Fish, Damhead Circlerooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated Apr 2023 | Feb 2023 | granted Apr 2023 | Apr 2023 | Aberdeenshire | 5.4 |
| St Fergus Renewable Energy Parkbattery storage | battery storage | — | under constructionupdated Feb 2023 | Dec 2019 | granted Jul 2021 | Feb 2023 | Aberdeenshire | 7.8 |
Distance from the average position of the AB42 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 7 | 0 | 6 | 0 | 0 | 108 |
| Rooftop solar | 1 | 0 | 1 | 0 | 0 | 0.3 |
| Wind farm | 8 | 0 | 2 | 4 | 0 | 10.1 |
| Wind turbine | 1 | 0 | 0 | 0 | 1 | 0 |
| Battery storage | 8 | 3 | 4 | 1 | 0 | 1,500 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Hywind Scotland Pilot Park (Hywind 2) Demonstrator | 30 | operationalupdated Jul 2018 | 27.0 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Aberdeenshire decides solar, wind and battery applications
| Applications | Aberdeenshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 200 | 10,236 |
| Refused | 64 (32%) | 19% |
| Solar refused | 1 of 40 | 12% |
| Onshore wind refused | 60 of 132 | 45% |
| Battery storage refused | 3 of 28 | 16% |
| Median time from submission to decision | 40.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 15 / 13 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near AB42, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.