St Fergus Moss Wind Farm (6 MW)

St Fergus Moss Wind Farm is a 6 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 18 December 2012; the record was last updated on 22 March 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWwind farm
operationalstatus in REPD
22 March 2013record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
28 June 2010Application submitted
23 February 2012Planning permission granted
31 March 2012Construction started
18 December 2012Operational

Project details

Technology
wind farm
Capacity
6 MW
Status (REPD)
operational
Record last updated
22 March 2013
Operator or applicant
Greenspan Electric St Fergus Ltd
Planning authority
Aberdeenshire
Planning application reference
APP/2010/2118
Turbines
3
Address (REPD)
Land at St Fergus Moss, St Fergus, Peterhead
Council area (by location)
Aberdeenshire
Time to decision
86 weeks
REPD reference
2741

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Overside and Greenwellheads Farmswind farm9.2operational1.3
South of Greenwellheadssolar farm5abandoned1.4
Greenside Extensionwind farm7approved, not built1.9
Bilbo Solar Farmsolar farm36.6under construction1.9
Bilbo Solar Farm Energy Storagebattery storage40under construction2.2
Frodo Solar and Battery Energy Developmentsolar farm60.1approved, not built3.3
St Fergus Renewable Energy Parksolar farm5under construction4.2
Fraserburgh Road - Kirkton Solar PV Farm & Energy Storage Facilitysolar farm50approved, not built4.3
Strichen Southbattery storage10abandoned6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.572, -1.9111).