Land at Overside and Greenwellheads Farms (9.2 MW wind farm)

Land at Overside and Greenwellheads Farms is a 9.2 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 November 2013; the record was last updated on 9 December 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.2 MWwind farm
operationalstatus in REPD
9 December 2013record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
30 March 2011Application submitted
13 September 2011Planning permission granted
1 November 2013Operational

Project details

Technology
wind farm
Capacity
9.2 MW
Status (REPD)
operational
Record last updated
9 December 2013
Operator or applicant
Greenside Wind Energy Ltd
Planning authority
Aberdeenshire
Planning application reference
APP/2011/1024
Turbines
4
Address (REPD)
Crimond, Fraserburgh, AB42 3HJ
Council area (by location)
Aberdeenshire
Time to decision
24 weeks
REPD reference
3802

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
South of Greenwellheadssolar farm5abandoned0.3
Greenside Extensionwind farm7approved, not built0.5
Bilbo Solar Farm Energy Storagebattery storage40under construction1.1
Bilbo Solar Farmsolar farm36.6under construction1.1
St Fergus Moss Wind Farmwind farm6operational1.3
Frodo Solar and Battery Energy Developmentsolar farm60.1approved, not built2.3
St Fergus Renewable Energy Parksolar farm5under construction3.9
Fraserburgh Road - Kirkton Solar PV Farm & Energy Storage Facilitysolar farm50approved, not built4.2
Strichen Southbattery storage10abandoned7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5822, -1.8993).