Energy Projects Near You

Frodo Solar and Battery Energy Development (60.1 MW)

Frodo Solar and Battery Energy Development is a 60.1 MW solar farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 May 2023, not yet built; the record was last updated on 12 April 2022. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

60.1 MWsolar farm
approved, not builtstatus in REPD
12 April 2022record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
16 March 2022Application submitted
16 May 2023Section 36 consent granted (Scottish Ministers)
16 May 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
60.1 MW
Status (REPD)
approved, not built
Record last updated
12 April 2022
Operator or applicant
Green Energy International
Planning authority
Scottish Government (S36)
Planning application reference
ECU00003345
Site area
113.0 ha
Address (REPD)
Frodo Solar Farm, Crimond, Fraserburgh
Council area (by location)
Aberdeenshire
Time to decision
61 weeks
REPD reference
10993

The scheme also includes 50 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Bilbo Solar Farm Energy Storagebattery storage40under construction1.3
Bilbo Solar Farmsolar farm36.6under construction1.3
Greenside Extensionwind farm7approved, not built2.0
Land at Overside and Greenwellheads Farmswind farm9.2operational2.3
South of Greenwellheadssolar farm5abandoned2.6
St Fergus Moss Wind Farmwind farm6operational3.3
St Fergus Renewable Energy Parksolar farm5under construction5.9
Fraserburgh Road - Kirkton Solar PV Farm & Energy Storage Facilitysolar farm50approved, not built6.3
Strichen Southbattery storage10abandoned6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.6012, -1.9152).