South of Greenwellheads (5 MW solar farm)

South of Greenwellheads is a 5 MW solar farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 29 July 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
abandonedstatus in REPD
29 July 2020record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
24 September 2015Application submitted
30 October 2015Planning permission granted
30 October 2018Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
abandoned
Record last updated
29 July 2020
Operator or applicant
Greenside Wind Energy
Planning authority
Aberdeenshire
Planning application reference
APP/2015/2949
Site area
10.6 ha
Address (REPD)
Land To The S/Of Greenwellhead, St. Fergus, Peterhead, Grampian
Council area (by location)
Aberdeenshire
Time to decision
5 weeks
REPD reference
5785

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Overside and Greenwellheads Farmswind farm9.2operational0.3
Greenside Extensionwind farm7approved, not built0.7
Bilbo Solar Farm Energy Storagebattery storage40under construction1.3
St Fergus Moss Wind Farmwind farm6operational1.4
Bilbo Solar Farmsolar farm36.6under construction1.4
Frodo Solar and Battery Energy Developmentsolar farm60.1approved, not built2.6
St Fergus Renewable Energy Parksolar farm5under construction3.6
Fraserburgh Road - Kirkton Solar PV Farm & Energy Storage Facilitysolar farm50approved, not built3.9
Salamander Offshore Wind Farm Battery Storage and Onshore Connectionbattery storage180approved, not built7.0