Energy Projects Near You

Bilbo Solar Farm (36.6 MW)

Bilbo Solar Farm is a 36.6 MW solar farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 December 2020; the record was last updated on 8 October 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36.6 MWsolar farm
under constructionstatus in REPD
8 October 2024record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
26 June 2019Application submitted
15 November 2019Planning permission granted
1 December 2020Construction started

Project details

Technology
solar farm
Capacity
36.6 MW
Status (REPD)
under construction
Record last updated
8 October 2024
Operator or applicant
Green Energy International
Planning authority
Aberdeenshire
Planning application reference
APP/2019/0296
Site area
50.8 ha
Address (REPD)
Land At Bilbo Solar Farm, Moss-side, Crimond, Fraserburgh, Grampian
Council area (by location)
Aberdeenshire
Time to decision
20 weeks
Contracts for Difference
AR6
REPD reference
6736

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bilbo Solar Farm Energy Storagebattery storage40under construction0.5
Greenside Extensionwind farm7approved, not built1.0
Land at Overside and Greenwellheads Farmswind farm9.2operational1.1
Frodo Solar and Battery Energy Developmentsolar farm60.1approved, not built1.3
South of Greenwellheadssolar farm5abandoned1.4
St Fergus Moss Wind Farmwind farm6operational1.9
St Fergus Renewable Energy Parksolar farm5under construction5.0
Fraserburgh Road - Kirkton Solar PV Farm & Energy Storage Facilitysolar farm50approved, not built5.3
Strichen Southbattery storage10abandoned6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5894, -1.9126).