Energy Projects Near You

St Fergus Renewable Energy Park (5 MW)

St Fergus Renewable Energy Park is a 5 MW solar farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 6 February 2023; the record was last updated on 1 February 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
under constructionstatus in REPD
1 February 2023record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
3 December 2019Application submitted
7 December 2020Refused by the planning authority
29 January 2021Appeal lodged
21 July 2021Planning permission granted
21 July 2021Appeal allowed
6 February 2023Construction started

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
under construction
Record last updated
1 February 2023
Operator or applicant
Ednie Farms
Planning authority
Aberdeenshire
Planning application reference
APP/2019/2653
Appeal reference
PPA-110-2407
Site area
11.6 ha
Address (REPD)
Land Adjacent To The St Fergus, St. Fergus, Peterhead,
Council area (by location)
Aberdeenshire
Time to decision
85 weeks
REPD reference
7596

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fraserburgh Road - Kirkton Solar PV Farm & Energy Storage Facilitysolar farm50approved, not built0.6
Salamander Offshore Wind Farm Battery Storage and Onshore Connectionbattery storage180approved, not built3.5
South of Greenwellheadssolar farm5abandoned3.6
Land at Overside and Greenwellheads Farmswind farm9.2operational3.9
Greenside Extensionwind farm7approved, not built4.0
St Fergus Moss Wind Farmwind farm6operational4.2
Bilbo Solar Farm Energy Storagebattery storage40under construction4.7
Bilbo Solar Farmsolar farm36.6under construction5.0
Frodo Solar and Battery Energy Developmentsolar farm60.1approved, not built5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5656, -1.8414).