St Fergus Renewable Energy Park (5 MW)
St Fergus Renewable Energy Park is a 5 MW solar farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 6 February 2023; the record was last updated on 1 February 2023.
5 MWsolar farm
under constructionstatus in REPD
1 February 2023record last updated
Aberdeenshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 3 December 2019 | Application submitted |
| 7 December 2020 | Refused by the planning authority |
| 29 January 2021 | Appeal lodged |
| 21 July 2021 | Planning permission granted |
| 21 July 2021 | Appeal allowed |
| 6 February 2023 | Construction started |
Project details
- Technology
- solar farm
- Capacity
- 5 MW
- Status (REPD)
- under construction
- Record last updated
- 1 February 2023
- Operator or applicant
- Ednie Farms
- Planning authority
- Aberdeenshire
- Planning application reference
- APP/2019/2653
- Appeal reference
- PPA-110-2407
- Site area
- 11.6 ha
- Address (REPD)
- Land Adjacent To The St Fergus, St. Fergus, Peterhead,
- Council area (by location)
- Aberdeenshire
- Time to decision
- 85 weeks
- REPD reference
- 7596
Who decides
| Applications | Aberdeenshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 200 | 10,236 |
| Refused | 64 (32%) | 19% |
| Solar refused | 1 of 40 | 12% |
| Onshore wind refused | 60 of 132 | 45% |
| Battery storage refused | 3 of 28 | 16% |
| Median time from submission to decision | 40.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 15 / 13 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Fraserburgh Road - Kirkton Solar PV Farm & Energy Storage Facility | solar farm | 50 | approved, not built | 0.6 |
| Salamander Offshore Wind Farm Battery Storage and Onshore Connection | battery storage | 180 | approved, not built | 3.5 |
| South of Greenwellheads | solar farm | 5 | abandoned | 3.6 |
| Land at Overside and Greenwellheads Farms | wind farm | 9.2 | operational | 3.9 |
| Greenside Extension | wind farm | 7 | approved, not built | 4.0 |
| St Fergus Moss Wind Farm | wind farm | 6 | operational | 4.2 |
| Bilbo Solar Farm Energy Storage | battery storage | 40 | under construction | 4.7 |
| Bilbo Solar Farm | solar farm | 36.6 | under construction | 5.0 |
| Frodo Solar and Battery Energy Development | solar farm | 60.1 | approved, not built | 5.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5656, -1.8414).