Energy Projects Near You

Greenside Extension (7 MW wind farm)

Greenside Extension is a 7 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 27 March 2025, not yet built; the record was last updated on 12 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWwind farm
approved, not builtstatus in REPD
12 May 2025record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
4 March 2024Application submitted
27 March 2025Planning permission granted

Project details

Technology
wind farm
Capacity
7 MW
Status (REPD)
approved, not built
Record last updated
12 May 2025
Operator or applicant
Greenside Wind Energy Limited
Planning authority
Aberdeenshire
Planning application reference
APP/2024/0229
Turbines
3
Turbine height
100 m
Address (REPD)
Overside & Greenwellheads Farms, Crimond, Fraserburgh, Peterhead
Council area (by location)
Aberdeenshire
Time to decision
55 weeks
Name in REPD
Greenside Extension - Wind Turbines
REPD reference
16083

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Overside and Greenwellheads Farmswind farm9.2operational0.5
South of Greenwellheadssolar farm5abandoned0.7
Bilbo Solar Farm Energy Storagebattery storage40under construction0.7
Bilbo Solar Farmsolar farm36.6under construction1.0
St Fergus Moss Wind Farmwind farm6operational1.9
Frodo Solar and Battery Energy Developmentsolar farm60.1approved, not built2.0
St Fergus Renewable Energy Parksolar farm5under construction4.0
Fraserburgh Road - Kirkton Solar PV Farm & Energy Storage Facilitysolar farm50approved, not built4.4
Strichen Southbattery storage10abandoned7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5868, -1.8965).