Energy Projects Near You

Salamander Offshore Wind Farm Battery Storage and Onshore Connection (180 MW)

Salamander Offshore Wind Farm Battery Storage and Onshore Connection is a 180 MW battery storage project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 28 October 2025, not yet built; the record was last updated on 18 November 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

180 MWbattery storage
approved, not builtstatus in REPD
18 November 2025record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
15 August 2024Application submitted
28 October 2025Section 36 consent granted (Scottish Ministers)

Project details

Technology
battery storage (co-located with re)
Capacity
180 MW
Status (REPD)
approved, not built
Record last updated
18 November 2025
Operator or applicant
Orsted / Simply Blue Group
Planning authority
Scottish Government (S36)
Planning application reference
ECU00005201
Address (REPD)
Lunderton, N/O Peterhead
Council area (by location)
Aberdeenshire
Time to decision
63 weeks
Name in REPD
Salamander Offshore Wind Farm - Battery Storage and Onshore Connection
REPD reference
18567

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Fraserburgh Road - Kirkton Solar PV Farm & Energy Storage Facilitysolar farm50approved, not built3.1
St Fergus Renewable Energy Parksolar farm5under construction3.5
South of Greenwellheadssolar farm5abandoned7.0
Flushing, Longsidebattery storage400application submitted7.0
St Fergus Moss Wind Farmwind farm6operational7.1
Land at Overside and Greenwellheads Farmswind farm9.2operational7.2
Netherton, Langside Roadbattery storage400application submitted7.3
Greenside Extensionwind farm7approved, not built7.5
Greystone, Blackhillsbattery storage500application submitted7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.539, -1.8085).