Energy Projects Near You

Solar, wind and battery projects near Turriff (AB53)

16 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of AB53 (Aberdeenshire): 2 are waiting for a planning decision, 1 approved but not yet running, 6 operational. The largest live scheme is Abbotshaugh Battery Storage (500 MW battery storage, application submitted on 16 May 2025, no decision recorded), 7.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16projects within 10 km
2awaiting a decision
1approved, not running
6operational

Projects within 10 km of AB53

Projects of 1 MW and more (14)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Burnside of Idochwind farmwind farm3.2refused on appealupdated Nov 2011Feb 2010refused Nov 2010Nov 2011Aberdeenshire0.7
Cairn Hillwind farmwind farm2.4refusedupdated Jun 2011Apr 2010refused Nov 2010Jun 2011Aberdeenshire4.1
Cairnhill Farm solar parksolar farmsolar farm2.4operationalupdated Feb 2016Apr 2013granted May 2013Feb 2016Aberdeenshire4.1
Whitestones, Cuminestown Solar Farmsolar farmsolar farm9.9approved, not builtupdated Feb 2026Apr 2025granted Jul 2025Feb 2026Aberdeenshire4.7
Backhill of Yonderton Wind Clusterwind farmwind farm4.6operationalupdated May 2015Nov 2010granted Nov 2012May 2015Aberdeenshire7.0
Bogenlea Farmwind turbinewind turbine2.3operationalupdated Sep 2014May 2009granted Dec 2009Sep 2014Aberdeenshire7.2
Abbotshaugh Battery Storagebattery storagebattery storage500application submittedupdated Jun 2025May 2025—Jun 2025Aberdeenshire7.5
Gairnieston Farmwind turbinewind turbine2.3operationalupdated Sep 2011Sep 2007granted Jul 2009Sep 2011Aberdeenshire7.8
Gordonstown Hill Wind Farmwind farmwind farm12.5operationalupdated Jun 2013Dec 2008granted Jul 2009Jun 2013Aberdeenshire8.8
Hill of Carlincraig wind turbineswind farmwind farm4.6permission expiredupdated Sep 2020Apr 2013granted Jul 2015Sep 2020Aberdeenshire8.9
Shielburn Farmwind farmwind farm6.9operationalupdated May 2013Dec 2009granted Oct 2012May 2013Aberdeenshire9.3
North Haddowind farmwind farm1.6permission expiredupdated Oct 2018Apr 2017—Oct 2018Aberdeenshire9.6
Hillhead of Bonnykellywind turbinewind turbine2.3refusedupdated Mar 2014Oct 2013refused Feb 2014Mar 2014Aberdeenshire9.7
Holm and Hollymill Wind Turbineswind farmwind farm4.6refusedupdated Mar 2014Jan 2012refused Jan 2014Mar 2014Aberdeenshire9.8
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Wagglehill, Cuminestownwind turbinewind turbine0.2refusedupdated Jul 2024Apr 2024refused Jun 2024Jul 2024Aberdeenshire3.2
Upper Mains Farmwind turbinewind turbine0.5application submitted may be out of dateupdated Nov 2023Nov 2023—Nov 2023Aberdeenshire5.8

Distance from the average position of the AB53 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm201109.9
Wind farm800330
Wind turbine510220.5
Battery storage11000500

MW in pipeline: pending, approved and under-construction capacity.

How Aberdeenshire decides solar, wind and battery applications

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

All projects in Aberdeenshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near AB53, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.