Abbotshaugh Battery Storage (500 MW)

Abbotshaugh Battery Storage is a 500 MW battery storage project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 16 May 2025, no decision recorded; the record was last updated on 27 June 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

500 MWbattery storage
application submittedstatus in REPD
27 June 2025record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
16 May 2025Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
500 MW
Status (REPD)
application submitted
Record last updated
27 June 2025
Operator or applicant
Island Green Power (IGP Solar 25 Limited)
Planning authority
Scottish Government (S36)
Planning application reference
ECU00005224
Address (REPD)
Abbotshaugh, New Deer, Turriff
Council area (by location)
Aberdeenshire
REPD reference
17552

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Whitestones, Cuminestown Solar Farmsolar farm9.9approved, not built5.5
Methlick Farmers Wind Energy Projectwind farm12operational8.4
Hill of Skilmafilly Cloffrickford (Denmore) Wind Farmwind farm6.9operational8.5
Cloffrickford Farmwind farm10application withdrawn9.4
Cloffrickfordwind farm9.2application withdrawn10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5014, -2.2756).