Cloffrickford (9.2 MW wind farm)
Cloffrickford is a 9.2 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 9 June 2010; the record was last updated on 9 June 2010.
9.2 MWwind farm
application withdrawnstatus in REPD
9 June 2010record last updated
Aberdeenshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 17 February 2010 | Application submitted |
| 9 June 2010 | Application withdrawn |
Project details
- Technology
- wind farm
- Capacity
- 9.2 MW
- Status (REPD)
- application withdrawn
- Record last updated
- 9 June 2010
- Operator or applicant
- Skelmonae Windfarm Ltd
- Planning authority
- Aberdeenshire
- Planning application reference
- APP/2009/1278
- Turbines
- 4
- Address (REPD)
- Auchnagatt (Denmore), Ellon, Grampian. AB41 8YD
- Council area (by location)
- Aberdeenshire
- REPD reference
- 2685
Who decides
| Applications | Aberdeenshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 200 | 10,236 |
| Refused | 64 (32%) | 19% |
| Solar refused | 1 of 40 | 12% |
| Onshore wind refused | 60 of 132 | 45% |
| Battery storage refused | 3 of 28 | 16% |
| Median time from submission to decision | 40.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 15 / 13 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Cloffrickford Farm | wind farm | 10 | application withdrawn | 0.6 |
| Hill of Skilmafilly Cloffrickford (Denmore) Wind Farm | wind farm | 6.9 | operational | 1.5 |
| Methlick Farmers Wind Energy Project | wind farm | 12 | operational | 6.3 |
| Kinmuck Battery Energy Storage | battery storage | 105 | approved, not built | 8.8 |
| Abbotshaugh Battery Storage | battery storage | 500 | application submitted | 10.0 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.4466, -2.1437).