Energy Projects Near You

Whitestones, Cuminestown Solar Farm (9.9 MW)

Whitestones, Cuminestown Solar Farm is a 9.9 MW solar farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 July 2025, not yet built; the record was last updated on 19 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.9 MWsolar farm
approved, not builtstatus in REPD
19 February 2026record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
7 April 2025Application submitted
22 July 2025Planning permission granted
22 July 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
9.9 MW
Status (REPD)
approved, not built
Record last updated
19 February 2026
Operator or applicant
Locogen Limited
Planning authority
Aberdeenshire
Planning application reference
APP/2025/0338
Site area
1.5 ha
Address (REPD)
Whitestones, Cuminestown, Turriff
Council area (by location)
Aberdeenshire
Time to decision
15 weeks
Contracts for Difference
AR7a
Name in REPD
Whitestones, Cuminestown - Solar Farm
REPD reference
17707

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Abbotshaugh Battery Storagebattery storage500application submitted5.5
Hill of Fishriewind farm11.3refused7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5444, -2.3228).