Hill of Fishrie (11.3 MW wind farm)

Hill of Fishrie is an 11.3 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 29 November 2013; the record was last updated on 21 January 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.3 MWwind farm
refusedstatus in REPD
21 January 2014record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
13 July 2011Application submitted
29 November 2013Refused by the planning authority

Project details

Technology
wind farm
Capacity
11.3 MW
Status (REPD)
refused
Record last updated
21 January 2014
Operator or applicant
Novera Energy
Planning authority
Aberdeenshire
Planning application reference
APP/2011/2249
Turbines
5
Address (REPD)
Bracklamore, Aberdeenshire, Grampian
Council area (by location)
Aberdeenshire
Time to decision
124 weeks
REPD reference
3762

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Whitestones, Cuminestown Solar Farmsolar farm9.9approved, not built7.9
Cairnandrewwind farm6refused8.0
Whitestones Birks Farm, Longmanhillbattery storage49.9refused10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.6137, -2.2967).