Energy Projects Near You

Solar, wind and battery projects near Huntly (AB54)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of AB54 (Aberdeenshire): 1 is waiting for a planning decision, 2 approved but not yet running, 3 operational. The largest live scheme is Hill of Stoneyfield (14.4 MW wind farm, application submitted on 6 May 2025, no decision recorded), 8.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
1awaiting a decision
2approved, not running
3operational

Projects within 10 km of AB54

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Dummuiewind farmwind farm12.3operationalupdated Jun 2015Aug 2003granted Feb 2004Jun 2015Aberdeenshire4.2
Mains Of Collithiewind farmwind farm2.4refusedupdated Nov 2014Mar 2014refused Aug 2014Nov 2014Aberdeenshire6.9
Hill of Corskiewind farmwind farm4.5refusedupdated Jan 2014Oct 2013refused Jan 2014Jan 2014Aberdeenshire8.0
Glens of Foudlandwind farmwind farm26operationalupdated Feb 2016Jan 2001granted Oct 2001Feb 2016Aberdeenshire8.1
Glens of Foudland Wind Farm (Extension)wind farmwind farm14application withdrawnupdated Mar 2015Aug 2015—Mar 2015Aberdeenshire8.2
Hill of Stoneyfieldwind farmwind farm14.4application submittedupdated Jun 2025May 2025—Jun 2025Aberdeenshire8.2
Cairnborrowwind farmwind farm10operationalupdated Apr 2018Oct 2013granted Aug 2014Apr 2018Aberdeenshire8.3
Stony Hillwind farmwind farm18application withdrawnupdated Jul 2015Jul 2013—Jul 2015Aberdeenshire9.5
Meikleton of Ardonaldwind turbinewind turbine1approved, not builtupdated Oct 2023Jun 2023granted Oct 2023Oct 2023Aberdeenshire9.6
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Rivestone, Kinnoirwind turbinewind turbine0.3approved, not builtupdated May 2025Dec 2024granted Apr 2025May 2025Moray5.8

Distance from the average position of the AB54 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm8103214.4
Wind turbine202001.3

MW in pipeline: pending, approved and under-construction capacity.

How Aberdeenshire decides solar, wind and battery applications

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

All projects in Aberdeenshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.