Stony Hill (18 MW wind farm)

Stony Hill is an 18 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 19 May 2015; the record was last updated on 1 July 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWwind farm
application withdrawnstatus in REPD
1 July 2015record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
4 July 2013Application submitted
19 May 2015Application withdrawn

Project details

Technology
wind farm
Capacity
18 MW
Status (REPD)
application withdrawn
Record last updated
1 July 2015
Operator or applicant
Stony Hill Wind Farm Ltd
Planning authority
Aberdeenshire
Planning application reference
APP/2013/2064
Turbines
5
Address (REPD)
Land at Stony Hill/RedHill, Lenchie, Insch, AB52 6NE
Council area (by location)
Aberdeenshire
REPD reference
4219

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hill of Stoneyfieldwind farm14.4application submitted3.4
Glens of Foudland Wind Farm (Extension)wind farm14application withdrawn4.1
Hill of Tillymorgan (Kirkton Farm) Wind turbineswind farm9.6operational6.1
Glens of Foudlandwind farm26operational6.2
Dummuiewind farm12.3operational8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.3779, -2.6903).