Hill of Tillymorgan (Kirkton Farm) Wind turbines (9.6 MW)

Hill of Tillymorgan (Kirkton Farm) Wind turbines is a 9.6 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2016; the record was last updated on 4 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.6 MWwind farm
operationalstatus in REPD
4 April 2017record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
16 March 2011Application submitted
30 April 2013Planning permission granted
1 July 2015Construction started
1 December 2016Operational

Project details

Technology
wind farm
Capacity
9.6 MW
Status (REPD)
operational
Record last updated
4 April 2017
Operator or applicant
LocoGen/ Green Cat Renewables
Planning authority
Aberdeenshire
Planning application reference
APP/2011/0855
Turbines
3
Address (REPD)
Hill of Tillymorgan, Culsalmond, Insch
Council area (by location)
Aberdeenshire
Time to decision
111 weeks
REPD reference
3911

Earlier applications for this site

ApplicationMWSubmittedOutcome
Hill of Tillymorgan APP/2008/014763 March 2008withdrawn 15 May 2013

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stony Hillwind farm18application withdrawn6.1
Hill of Stoneyfieldwind farm14.4application submitted7.3
Glens of Foudland Wind Farm (Extension)wind farm14application withdrawn7.7
Overhill Farm, Rothienormanbattery storage49.9under construction8.5
Middleton Of Blackhills, Rothienormanbattery storage49.9application submitted8.5
Fairfieldbattery storage49.9refused9.1
Glens of Foudlandwind farm26operational9.2
Redhill Farmswind farm6refused9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.3441, -2.6104).