Overhill Farm, Rothienorman (49.9 MW battery storage)

Overhill Farm, Rothienorman is a 49.9 MW battery storage project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 September 2025; the record was last updated on 30 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
under constructionstatus in REPD
30 September 2025record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
2 November 2022Application submitted
1 March 2023Planning permission granted
1 September 2025Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
under construction
Record last updated
30 September 2025
Operator or applicant
One Planet Developments Limited
Planning authority
Aberdeenshire
Planning application reference
APP/2022/2252
Address (REPD)
Overhill Farm Rothienorman Inverurie
Council area (by location)
Aberdeenshire
Time to decision
17 weeks
Name in REPD
Overhill Farm, Rothienorman - Battery Energy Storage
REPD reference
11590

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Middleton Of Blackhills, Rothienormanbattery storage49.9application submitted<0.1
Redhill Farmswind farm6refused1.6
Fairfieldbattery storage49.9refused3.3
Rothienormanbattery storage49.9approved, not built3.5
Hassiewellswind farm6.9refused on appeal5.9
Gordonstown Hill Wind Farmwind farm12.5operational6.9
Glens of Foudlandwind farm26operational7.3
Floors Farm Wind Turbineswind farm6.9refused7.4
Glens of Foudland Wind Farm (Extension)wind farm14application withdrawn7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.4035, -2.5217).