Floors Farm Wind Turbines (6.9 MW)
Floors Farm Wind Turbines is a 6.9 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 26 May 2015; the record was last updated on 1 July 2015.
6.9 MWwind farm
refusedstatus in REPD
1 July 2015record last updated
Aberdeenshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 30 November 2012 | Application submitted |
| 26 May 2015 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 6.9 MW
- Status (REPD)
- refused
- Record last updated
- 1 July 2015
- Operator or applicant
- artine Partnership Ltd
- Planning authority
- Aberdeenshire
- Planning application reference
- APP/2012/3956
- Turbines
- 3
- Address (REPD)
- Floors Farm Auchterless Fortrie Turriff AB53 4HP
- Council area (by location)
- Aberdeenshire
- Time to decision
- 130 weeks
- REPD reference
- 4540
Who decides
| Applications | Aberdeenshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 200 | 10,236 |
| Refused | 64 (32%) | 19% |
| Solar refused | 1 of 40 | 12% |
| Onshore wind refused | 60 of 132 | 45% |
| Battery storage refused | 3 of 28 | 16% |
| Median time from submission to decision | 40.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 15 / 13 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Hassiewells | wind farm | 6.9 | refused on appeal | 2.2 |
| Shielburn Farm | wind farm | 6.9 | operational | 3.5 |
| Gordonstown Hill Wind Farm | wind farm | 12.5 | operational | 3.8 |
| Redhill Farms | wind farm | 6 | refused | 5.8 |
| Glens of Foudland | wind farm | 26 | operational | 7.2 |
| Overhill Farm, Rothienorman | battery storage | 49.9 | under construction | 7.4 |
| Middleton Of Blackhills, Rothienorman | battery storage | 49.9 | application submitted | 7.4 |
| Rothienorman | battery storage | 49.9 | approved, not built | 7.6 |
| Dummuie | wind farm | 12.3 | operational | 8.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.4686, -2.5455).