Energy Projects Near You

Floors Farm Wind Turbines (6.9 MW)

Floors Farm Wind Turbines is a 6.9 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 26 May 2015; the record was last updated on 1 July 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.9 MWwind farm
refusedstatus in REPD
1 July 2015record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
30 November 2012Application submitted
26 May 2015Refused by the planning authority

Project details

Technology
wind farm
Capacity
6.9 MW
Status (REPD)
refused
Record last updated
1 July 2015
Operator or applicant
artine Partnership Ltd
Planning authority
Aberdeenshire
Planning application reference
APP/2012/3956
Turbines
3
Address (REPD)
Floors Farm Auchterless Fortrie Turriff AB53 4HP
Council area (by location)
Aberdeenshire
Time to decision
130 weeks
REPD reference
4540

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hassiewellswind farm6.9refused on appeal2.2
Shielburn Farmwind farm6.9operational3.5
Gordonstown Hill Wind Farmwind farm12.5operational3.8
Redhill Farmswind farm6refused5.8
Glens of Foudlandwind farm26operational7.2
Overhill Farm, Rothienormanbattery storage49.9under construction7.4
Middleton Of Blackhills, Rothienormanbattery storage49.9application submitted7.4
Rothienormanbattery storage49.9approved, not built7.6
Dummuiewind farm12.3operational8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.4686, -2.5455).