Redhill Farms (6 MW wind farm)

Redhill Farms is a 6 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 19 May 2014; the record was last updated on 19 May 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWwind farm
refusedstatus in REPD
19 May 2014record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
10 December 2013Application submitted
19 May 2014Refused by the planning authority

Project details

Technology
wind farm
Capacity
6 MW
Status (REPD)
refused
Record last updated
19 May 2014
Operator or applicant
Clearwinds
Planning authority
Aberdeenshire
Planning application reference
APP/2013/3856
Turbines
3
Address (REPD)
Site to South West of East Redhill, Rothienorman, Inverurie
Council area (by location)
Aberdeenshire
Time to decision
23 weeks
REPD reference
3650

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Overhill Farm, Rothienormanbattery storage49.9under construction1.6
Middleton Of Blackhills, Rothienormanbattery storage49.9application submitted1.6
Rothienormanbattery storage49.9approved, not built4.1
Hassiewellswind farm6.9refused on appeal4.3
Fairfieldbattery storage49.9refused4.9
Floors Farm Wind Turbineswind farm6.9refused5.8
Gordonstown Hill Wind Farmwind farm12.5operational5.9
Glens of Foudlandwind farm26operational6.2
Glens of Foudland Wind Farm (Extension)wind farm14application withdrawn7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.4165, -2.5347).