Energy Projects Near You

Rothienorman (49.9 MW battery storage)

Rothienorman is a 49.9 MW battery storage project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 14 November 2022, not yet built; the record was last updated on 16 February 2022. REPD also records that the planning permission expired on 14 November 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtmay be out of datestatus in REPD
16 February 2022record last updated
Aberdeenshirecouncil area

REPD also records that the planning permission expired on 14 November 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
9 June 2022Application submitted
14 November 2022Planning permission granted
14 November 2025Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
16 February 2022
Operator or applicant
Anesco Limited
Planning authority
Aberdeenshire
Planning application reference
APP/2022/1218
Address (REPD)
1.5km To The North West Of Rothienorman
Council area (by location)
Aberdeenshire
Time to decision
23 weeks
Name in REPD
Rothienorman - Battery Storage
REPD reference
10638

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fairfieldbattery storage49.9refused3.4
Middleton Of Blackhills, Rothienormanbattery storage49.9application submitted3.5
Overhill Farm, Rothienormanbattery storage49.9under construction3.5
Redhill Farmswind farm6refused4.1
Gordonstown Hill Wind Farmwind farm12.5operational5.4
Rothienorman, Middleton of Blackhillsbattery storage500application submitted6.1
Hassiewellswind farm6.9refused on appeal7.1
Floors Farm Wind Turbineswind farm6.9refused7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.4146, -2.4663).