Energy Projects Near You

Fairfield (49.9 MW battery storage)

Fairfield is a 49.9 MW battery storage project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 25 February 2026; the record was last updated on 27 April 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
refusedstatus in REPD
27 April 2026record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
15 July 2025Application submitted
25 February 2026Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
refused
Record last updated
27 April 2026
Operator or applicant
Green Switch Capital
Planning authority
Aberdeenshire
Planning application reference
APP/2025/1015
Address (REPD)
Fairfield, Inverurie
Council area (by location)
Aberdeenshire
Time to decision
32 weeks
Name in REPD
Fairfield - Battery Energy Storage System
REPD reference
17254

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Middleton Of Blackhills, Rothienormanbattery storage49.9application submitted3.3
Overhill Farm, Rothienormanbattery storage49.9under construction3.3
Rothienormanbattery storage49.9approved, not built3.4
Rothienorman, Middleton of Blackhillsbattery storage500application submitted4.9
Redhill Farmswind farm6refused4.9
Gordonstown Hill Wind Farmwind farm12.5operational8.6
Hassiewellswind farm6.9refused on appeal9.0
Hill of Tillymorgan (Kirkton Farm) Wind turbineswind farm9.6operational9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.3845, -2.4793).