Energy Projects Near You

Middleton Of Blackhills, Rothienorman (49.9 MW battery storage)

Middleton Of Blackhills, Rothienorman is a 49.9 MW battery storage project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 3 April 2025, no decision recorded; the record was last updated on 25 April 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
application submittedstatus in REPD
25 April 2025record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
3 April 2025Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
25 April 2025
Operator or applicant
Scot Stability Limited
Planning authority
Aberdeenshire
Planning application reference
APP/2025/0415
Address (REPD)
Middleton Of Blackhills Rothienorman
Council area (by location)
Aberdeenshire
Name in REPD
Middleton Of Blackhills, Rothienorman - Battery Energy Storage System
REPD reference
18572

Earlier applications for this site

ApplicationMWSubmittedOutcome
Middleton Of Blackhills, Rothienorman APP/2023/071849.911 May 2023replaced by a revised application

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Overhill Farm, Rothienormanbattery storage49.9under construction<0.1
Redhill Farmswind farm6refused1.6
Fairfieldbattery storage49.9refused3.3
Rothienormanbattery storage49.9approved, not built3.5
Hassiewellswind farm6.9refused on appeal5.9
Gordonstown Hill Wind Farmwind farm12.5operational6.9
Glens of Foudlandwind farm26operational7.3
Floors Farm Wind Turbineswind farm6.9refused7.4
Glens of Foudland Wind Farm (Extension)wind farm14application withdrawn7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.4035, -2.5217).