Dummuie (12.3 MW wind farm)
Dummuie is a 12.3 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 January 2007; the record was last updated on 4 June 2015.
12.3 MWwind farm
operationalstatus in REPD
4 June 2015record last updated
Aberdeenshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 20 August 2003 | Application submitted |
| 20 February 2004 | Planning permission granted |
| 1 June 2006 | Construction started |
| 1 January 2007 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 12.3 MW
- Status (REPD)
- operational
- Record last updated
- 4 June 2015
- Operator or applicant
- Tetro Energy Ltd (ECO2)
- Planning authority
- Aberdeenshire
- Planning application reference
- APP/2003/0084
- Turbines
- 7
- Address (REPD)
- East Dummuie Huntly
- Council area (by location)
- Aberdeenshire
- Time to decision
- 26 weeks
- REPD reference
- 3200
Who decides
| Applications | Aberdeenshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 200 | 10,236 |
| Refused | 64 (32%) | 19% |
| Solar refused | 1 of 40 | 12% |
| Onshore wind refused | 60 of 132 | 45% |
| Battery storage refused | 3 of 28 | 16% |
| Median time from submission to decision | 40.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 15 / 13 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Glens of Foudland | wind farm | 26 | operational | 4.4 |
| Glens of Foudland Wind Farm (Extension) | wind farm | 14 | application withdrawn | 5.2 |
| Hill of Stoneyfield | wind farm | 14.4 | application submitted | 5.6 |
| Hassiewells | wind farm | 6.9 | refused on appeal | 7.7 |
| Stony Hill | wind farm | 18 | application withdrawn | 8.1 |
| Floors Farm Wind Turbines | wind farm | 6.9 | refused | 8.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.4511, -2.6915).