Energy Projects Near You

Solar, wind and battery projects near Keith (AB55)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of AB55 (Moray): 2 are waiting for a planning decision, 5 approved but not yet running, 2 operational. The largest live scheme is Gibson Farm, Blackhillock (349 MW battery storage, approved on 3 December 2025, not yet built), 2.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
2awaiting a decision
5approved, not running
2operational

Projects within 10 km of AB55

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bodinfinnoch Wind Farmwind farmwind farm13.8refused on appealupdated Jan 2014Sep 2011refused Dec 2012Jan 2014Moray1.3
Blackhillock Electricity Substationbattery storagebattery storage300under constructionupdated Sep 2021Dec 2021granted Feb 2022Sep 2021Moray2.5
Edintore Wind Farmwind farmwind farm18operationalupdated Oct 2016Dec 2010granted Aug 2012Oct 2016Moray2.6
Aultmore Forest - Buckie - Windfarmwind farmwind farm106application submitted may be out of dateupdated Mar 2024Feb 2024—Mar 2024Moray2.7
Aultmore Forest - Buckie - Windfarmbattery storagebattery storage50application submitted may be out of dateupdated Mar 2024Feb 2024—Mar 2024Moray2.7
Gibson Farm, Blackhillockbattery storagebattery storage349approved, not builtupdated Jan 2026Sep 2024granted Dec 2025Jan 2026Moray2.9
Electricity Substation, Westerton Roadbattery storagebattery storage49.9approved, not builtupdated Mar 2023Oct 2022granted Mar 2023Mar 2023Moray3.6
Drum Farmbattery storagebattery storage49.9approved, not builtupdated Jul 2025May 2022granted Oct 2022Jul 2025Moray4.0
Meikleton of Ardonaldwind turbinewind turbine1approved, not builtupdated Oct 2023Jun 2023granted Oct 2023Oct 2023Aberdeenshire6.6
Cairnborrowwind farmwind farm10operationalupdated Apr 2018Oct 2013granted Aug 2014Apr 2018Aberdeenshire8.6

Distance from the average position of the AB55 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm41021106
Wind turbine101001
Battery storage51400799

MW in pipeline: pending, approved and under-construction capacity.

How Moray decides solar, wind and battery applications

ApplicationsMorayUK
Decided applications (solar, wind, battery)2110,236
Refused7 (33%)19%
Solar refused0 of 212%
Onshore wind refused7 of 1445%
Battery storage refused0 of 516%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed4 / 6—

All projects in Moray

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near AB55, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.