Energy Projects Near You

Blackhillock Electricity Substation (300 MW battery storage)

Blackhillock Electricity Substation is a 300 MW battery storage project in Moray, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 February 2023; the record was last updated on 28 September 2021. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

300 MWbattery storage
under constructionstatus in REPD
28 September 2021record last updated
Moraycouncil area

Planning timeline

DateStage
23 December 2021Application submitted
28 February 2022Section 36 consent granted (Scottish Ministers)
1 February 2023Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
300 MW
Status (REPD)
under construction
Record last updated
28 September 2021
Operator or applicant
Zenobe Energy Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00003404
Address (REPD)
400m SE/O Blackhillock Electricity Substation, Keith
Council area (by location)
Moray
Time to decision
10 weeks
Name in REPD
Blackhillock Electricity Substation - Battery Energy Storage System
REPD reference
9723

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Aultmore Forest - Buckie - Windfarmwind farm106application submitted0.8
Aultmore Forest - Buckie - Windfarmbattery storage50application submitted0.8
Edintore Wind Farmwind farm18operational1.7
Electricity Substation, Westerton Roadbattery storage49.9approved, not built2.6
Gibson Farm, Blackhillockbattery storage349approved, not built2.7
Drum Farmbattery storage49.9approved, not built2.9
Bodinfinnoch Wind Farmwind farm13.8refused on appeal3.9
Cairnborrowwind farm10operational6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5184, -2.9475).