Electricity Substation, Westerton Road (49.9 MW battery storage)

Electricity Substation, Westerton Road is a 49.9 MW battery storage project in Moray, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 March 2023, not yet built; the record was last updated on 20 March 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
20 March 2023record last updated
Moraycouncil area

Planning timeline

DateStage
13 October 2022Application submitted
15 March 2023Planning permission granted
15 March 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
20 March 2023
Operator or applicant
Keith Renewables Limited
Planning authority
Moray
Planning application reference
22/01488/APP
Address (REPD)
Adjacent To Electricity Substation Westerton Road
Council area (by location)
Moray
Time to decision
22 weeks
Name in REPD
Electricity Substation, Westerton Road - Battery Storage
REPD reference
12467

Who decides

ApplicationsMorayUK
Decided applications (solar, wind, battery)2110,236
Refused7 (33%)19%
Solar refused0 of 212%
Onshore wind refused7 of 1445%
Battery storage refused0 of 516%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed4 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Drum Farmbattery storage49.9approved, not built0.4
Gibson Farm, Blackhillockbattery storage349approved, not built1.0
Aultmore Forest - Buckie - Windfarmwind farm106application submitted1.8
Aultmore Forest - Buckie - Windfarmbattery storage50application submitted1.8
Blackhillock Electricity Substationbattery storage300under construction2.6
Edintore Wind Farmwind farm18operational4.2
Bodinfinnoch Wind Farmwind farm13.8refused on appeal4.5
Cairnborrowwind farm10operational8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5409, -2.9362).