Energy Projects Near You

Cairnborrow (10 MW wind farm)

Cairnborrow is a 10 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 9 February 2017; the record was last updated on 3 April 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWwind farm
operationalstatus in REPD
3 April 2018record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
9 October 2013Application submitted
25 August 2014Planning permission granted
12 August 2015Construction started
9 February 2017Operational

Project details

Technology
wind farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
3 April 2018
Operator or applicant
Engie (GDF Suez)
Planning authority
Aberdeenshire
Planning application reference
APP/2013/3282
Turbines
5
Turbine height
100 m
Address (REPD)
Land at Cairnborrow Huntly
Council area (by location)
Aberdeenshire
Time to decision
46 weeks
REPD reference
4350

Earlier applications for this site

ApplicationMWSubmittedOutcome
Cairnborrow APP/2011/1639252 June 2011refused 31 August 2012

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Edintore Wind Farmwind farm18operational6.0
Blackhillock Electricity Substationbattery storage300under construction6.7
Aultmore Forest - Buckie - Windfarmbattery storage50application submitted7.3
Aultmore Forest - Buckie - Windfarmwind farm106application submitted7.3
Electricity Substation, Westerton Roadbattery storage49.9approved, not built8.8
Drum Farmbattery storage49.9approved, not built9.0
Clashindarroch 2wind farm77approved, not built9.1
Gibson Farm, Blackhillockbattery storage349approved, not built9.3
Bodinfinnoch Wind Farmwind farm13.8refused on appeal9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.4639, -2.8992).