Energy Projects Near You

Gibson Farm, Blackhillock (349 MW battery storage)

Gibson Farm, Blackhillock is a 349 MW battery storage project in Moray, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 3 December 2025, not yet built; the record was last updated on 9 January 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

349 MWbattery storage
approved, not builtstatus in REPD
9 January 2026record last updated
Moraycouncil area

Planning timeline

DateStage
27 September 2024Application submitted
3 December 2025Section 36 consent granted (Scottish Ministers)
3 December 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
349 MW
Status (REPD)
approved, not built
Record last updated
9 January 2026
Operator or applicant
Noriker Power Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00005237
Address (REPD)
Gibsons Farm, Blackhillock, Keith
Council area (by location)
Moray
Time to decision
62 weeks
Name in REPD
Gibson Farm, Blackhillock - Battery Energy Storage System
REPD reference
14283

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Electricity Substation, Westerton Roadbattery storage49.9approved, not built1.0
Drum Farmbattery storage49.9approved, not built1.4
Aultmore Forest - Buckie - Windfarmwind farm106application submitted2.1
Aultmore Forest - Buckie - Windfarmbattery storage50application submitted2.1
Blackhillock Electricity Substationbattery storage300under construction2.7
Bodinfinnoch Wind Farmwind farm13.8refused on appeal3.6
Edintore Wind Farmwind farm18operational4.2
Cairnborrowwind farm10operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5428, -2.9528).