Bodinfinnoch Wind Farm (13.8 MW)
Bodinfinnoch Wind Farm is a 13.8 MW wind farm project in Moray, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 21 November 2013; the record was last updated on 30 January 2014.
13.8 MWwind farm
refused on appealstatus in REPD
30 January 2014record last updated
Moraycouncil area
Planning timeline
| Date | Stage |
|---|---|
| 8 September 2011 | Application submitted |
| 7 December 2012 | Refused by the planning authority |
| 21 November 2013 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 13.8 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 30 January 2014
- Operator or applicant
- Bidwells
- Planning authority
- Moray
- Planning application reference
- 11/01509/APP
- Turbines
- 6
- Address (REPD)
- Bodinfinnoch Farm, Keith, Moray
- Council area (by location)
- Moray
- Time to decision
- 65 weeks
- REPD reference
- 3620
Who decides
| Applications | Moray | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 21 | 10,236 |
| Refused | 7 (33%) | 19% |
| Solar refused | 0 of 2 | 12% |
| Onshore wind refused | 7 of 14 | 45% |
| Battery storage refused | 0 of 5 | 16% |
| Median time from submission to decision | 60.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 6 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Gibson Farm, Blackhillock | battery storage | 349 | approved, not built | 3.6 |
| Edintore Wind Farm | wind farm | 18 | operational | 3.9 |
| Blackhillock Electricity Substation | battery storage | 300 | under construction | 3.9 |
| Aultmore Forest - Buckie - Windfarm | wind farm | 106 | application submitted | 3.9 |
| Aultmore Forest - Buckie - Windfarm | battery storage | 50 | application submitted | 3.9 |
| Electricity Substation, Westerton Road | battery storage | 49.9 | approved, not built | 4.5 |
| Drum Farm | battery storage | 49.9 | approved, not built | 4.9 |
| Cairnborrow | wind farm | 10 | operational | 9.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5298, -3.0089).