Renewable energy projects in Moray

46 solar, wind or battery projects of 150 kW or more are located in Moray (REPD, July 2026 extract): 13 pending, 17 approved but not running, 8 operational and 3 refused. The council refused 7 of 21 decided applications (33%; UK 19%), with a median 61 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

46projects in the council area
13awaiting a decision
17approved, not running
33%of decisions refused

How Moray decides

ApplicationsMorayUK
Decided applications (solar, wind, battery)2110,236
Refused7 (33%)19%
Solar refused0 of 212%
Onshore wind refused7 of 1445%
Battery storage refused0 of 516%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed4 / 6—

Projects in Moray

Projects of 1 MW and more (43)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Dorenell Extension Wind Farmwind farmwind farm477application submittedupdated Oct 2025Aug 2025—Oct 2025
Gibson Farm, Blackhillockbattery storagebattery storage349approved, not builtupdated Jan 2026Sep 2024granted Dec 2025Jan 2026
Blackhillock Electricity Substationbattery storagebattery storage300under constructionupdated Sep 2021Dec 2021granted Feb 2022Sep 2021
Dorenell Wind Farm (Previously Site A and B Scaut Hill)wind farmwind farm177operationalupdated Jul 2019May 2008granted Jan 2012Jul 2019
Dorenell Wind Farm (extension)wind farmwind farm175abandonedupdated Apr 2018Dec 2014refused Jun 2016Apr 2018
Clashindarroch Wind Farm Extensionwind farmwind farm139approved, not builtupdated Jan 2026Jan 2023granted Dec 2025Jan 2026
Rothes Wind Farm IIIwind farmwind farm132approved, not builtupdated Oct 2022Feb 2019granted Oct 2022Oct 2022
Aultmore Forest - Buckie - Windfarmwind farmwind farm106application submitted may be out of dateupdated Mar 2024Feb 2024—Mar 2024
Teindland Wind Farmwind farmwind farm85application submittedupdated Aug 2025Jul 2025—Aug 2025
Craig Watch Wind Farm & Battery Storagewind farmwind farm72.6application submitted may be out of dateupdated Jul 2022Jun 2022—Jul 2022
Rothes Wind (Cairn Uish)wind farmwind farm50.6operationalupdated May 2017Sep 2001granted Jan 2003May 2017
Milltown Airfield (Speyslaw)solar farmsolar farm50approved, not built may be out of dateupdated Sep 2020Jul 2017granted May 2018Sep 2020
Aultmore Forest - Buckie - Windfarmbattery storagebattery storage50application submitted may be out of dateupdated Mar 2024Feb 2024—Mar 2024
Drum Farmbattery storagebattery storage49.9approved, not builtupdated Jul 2025May 2022granted Oct 2022Jul 2025
Electricity Substation, Westerton Roadbattery storagebattery storage49.9approved, not builtupdated Mar 2023Oct 2022granted Mar 2023Mar 2023
Loanhead Farmbattery storagebattery storage49.9application submittedupdated Jun 2025May 2025—Jun 2025
Hill of Towie (Drummuir)wind farmwind farm48operationalupdated Jun 2020Nov 2002granted Nov 2003Jun 2020
Hill of Towie II Wind Farmwind farmwind farm48permission expiredupdated Jun 2020Oct 2013granted Jun 2017Jun 2020
Garbet Windfarm Wind Farm & Storage facilitywind farmwind farm46.2under constructionupdated Jul 2025Jan 2021granted Nov 2021Jul 2025
Blackhills Wind Farmwind farmwind farm43.2application submittedupdated Oct 2025Aug 2025—Oct 2025
Rothes Wind Farm (Extension) (II)wind farmwind farm41.4operationalupdated Aug 2013Dec 2007granted Jan 2010Aug 2013
Kellas Wind Farmwind farmwind farm38.4approved, not builtupdated Jun 2026Mar 2024granted Jan 2026Jun 2026
Brown Muir Wind Farm (resubmission)wind farmwind farm36refused on appealupdated May 2016Nov 2014refused Sep 2015May 2016
Bishopmillbattery storagebattery storage30approved, not builtupdated Jan 2024Jun 2023granted Dec 2023Jan 2024
Kellas Wind Farmbattery storagebattery storage30approved, not builtupdated Jun 2026Mar 2024granted Jan 2026Jun 2026
Hill of Glaschyle Wind Farmwind farmwind farm27.6operationalupdated Apr 2017Jan 2013granted Mar 2014Apr 2017
Craig Watch Wind Farm & Battery Storagebattery storagebattery storage27.4application submitted may be out of dateupdated Jul 2022Jun 2022—Jul 2022
Cairn Uish Wind Farm Extensionwind farmwind farm21application withdrawnupdated Aug 2004——Aug 2004
Speyslaw Solar Farmsolar farmsolar farm20approved, not built may be out of dateupdated Sep 2020May 2017granted Aug 2017Sep 2020
Dorenell Extension Wind Farmbattery storagebattery storage20application submittedupdated Oct 2025Aug 2025—Oct 2025
Blackhills Wind Farmbattery storagebattery storage20application submittedupdated Oct 2025Aug 2025—Oct 2025
Speyslaw Farmbattery storagebattery storage19.9approved, not built may be out of dateupdated Mar 2023Dec 2021granted Feb 2023Mar 2023
Kellas Wind Farmwind farmwind farm18.4permission expiredupdated Mar 2022Apr 2013granted Nov 2014Mar 2022
Edintore Wind Farmwind farmwind farm18operationalupdated Oct 2016Dec 2010granted Aug 2012Oct 2016
Lurg Hill Wind Farmwind farmwind farm15approved, not built may be out of dateupdated Sep 2019Sep 2017granted Feb 2019Sep 2019
Bodinfinnoch Wind Farmwind farmwind farm13.8refused on appealupdated Jan 2014Sep 2011refused Dec 2012Jan 2014
Meikle Hill wind farmwind farmwind farm13.8permission expiredupdated Oct 2018Jun 2014granted Jun 2015Oct 2018
RAF Lossiemouthsolar farmsolar farm5application submittedupdated Jul 2026May 2026—Jul 2026
Netherton of Windyhillswind farmwind farm4.6operationalupdated Mar 2015Jun 2009granted Oct 2010Mar 2015
Craigellachie Biomass CHP Plant, Craigellachie- Solar Farmsolar farmsolar farm4approved, not builtupdated Jan 2024Sep 2023granted Jan 2024Jan 2024
Garbet Windfarm Wind Farm & Storage facilitybattery storagebattery storage3under constructionupdated Jul 2025Jan 2021granted Nov 2021Jul 2025
Netherton Of Windyhills (extension)wind turbinewind turbine2.3refusedupdated Apr 2014Oct 2012refused Feb 2014Apr 2014
Myreton Crossroadswind farmwind farm1.6operationalupdated Sep 2013Feb 2009granted Jul 2010Sep 2013
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Rivestone, Kinnoirwind turbinewind turbine0.3approved, not builtupdated May 2025Dec 2024granted Apr 2025May 2025
Teindland Wind Farmwind farmwind farm—application submittedupdated Aug 2025Jul 2025—Aug 2025
Scottish Water Treatment Plant, Moycroft Roadrooftop solarrooftop solar—application submittedupdated May 2026Apr 2026—May 2026

Postcode districts in Moray

DistrictProjects within 10 kmPendingApprovedOperational
AB372200
AB3811442
AB5510252
AB564012
IV3011541
IV317340
IV326230
IV360000

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Moray by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.