Hill of Towie II Wind Farm (48 MW)

Hill of Towie II Wind Farm is a 48 MW wind farm project in Moray, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 16 June 2022; the record was last updated on 25 June 2020. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

48 MWwind farm
permission expiredstatus in REPD
25 June 2020record last updated
Moraycouncil area

Planning timeline

DateStage
31 October 2013Application submitted
28 January 2015Appeal lodged
16 June 2017Section 36 consent granted (Scottish Ministers)
16 June 2017Appeal allowed
16 June 2022Permission expired

Project details

Technology
wind farm
Capacity
48 MW
Status (REPD)
permission expired
Record last updated
25 June 2020
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Appeal reference
WIN-300-1
Turbines
16
Address (REPD)
Hill of Towie, Knockan and McHattie's Cairn, Drummuir, Keith, Banffshire, Moray
Council area (by location)
Moray
Time to decision
189 weeks
REPD reference
4589

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Hill of Towie (Drummuir)wind farm48operational<0.1
Loanhead Farmbattery storage49.9application submitted5.1
Bishopmillbattery storage30approved, not built5.5
Kellas Wind Farmwind farm18.4permission expired6.9
Kellas Wind Farmwind farm38.4approved, not built7.3
Kellas Wind Farmbattery storage30approved, not built7.3
Blackhills Wind Farmwind farm43.2application submitted7.7
Milltown Airfield (Speyslaw)solar farm50approved, not built8.4
Brown Muir Wind Farm (resubmission)wind farm36refused on appeal8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.6228, -3.341).