Brown Muir Wind Farm (resubmission) (36 MW)

Brown Muir Wind Farm (resubmission) is a 36 MW wind farm project in Moray, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 26 May 2016; the record was last updated on 27 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36 MWwind farm
refused on appealstatus in REPD
27 May 2016record last updated
Moraycouncil area

Planning timeline

DateStage
10 November 2014Application submitted
18 September 2015Refused by the planning authority
15 December 2015Appeal lodged
26 May 2016Appeal refused

Project details

Technology
wind farm
Capacity
36 MW
Status (REPD)
refused on appeal
Record last updated
27 May 2016
Operator or applicant
Vento Ludens
Planning authority
Moray
Planning application reference
14/02090/EIA
Appeal reference
PPA-300-2044
Turbines
12
Turbine height
126 m
Address (REPD)
Land At Brown Muir Blackhills Elgin Moray
Council area (by location)
Moray
Time to decision
45 weeks
REPD reference
3343

Earlier applications for this site

ApplicationMWSubmittedOutcome
Brown Muir Wind Farm5720 June 2012withdrawn 15 August 2013

Who decides

ApplicationsMorayUK
Decided applications (solar, wind, battery)2110,236
Refused7 (33%)19%
Solar refused0 of 212%
Onshore wind refused7 of 1445%
Battery storage refused0 of 516%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed4 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Blackhills Wind Farmwind farm43.2application submitted3.0
Teindland Wind Farmwind farm85application submitted5.7
Hill of Towie (Drummuir)wind farm48operational8.8
Hill of Towie II Wind Farmwind farm48permission expired8.8
Rothes Wind Farm IIIwind farm132approved, not built9.1
Kellas Wind Farmbattery storage30approved, not built9.4
Kellas Wind Farmwind farm38.4approved, not built9.4
Rothes Wind Farm (Extension) (II)wind farm41.4operational9.6
Rothes Wind (Cairn Uish)wind farm50.6operational9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5772, -3.2211).