Energy Projects Near You

Solar, wind and battery projects near Elgin (IV30)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IV30 (Moray): 5 are waiting for a planning decision, 4 approved but not yet running, 1 operational. The largest live scheme is Milltown Airfield (Speyslaw) (50 MW solar farm, approved on 25 May 2018, not yet built; REPD status may be out of date), 5.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
5awaiting a decision
4approved, not running
1operational

Projects within 10 km of IV30

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bishopmillbattery storagebattery storage30approved, not builtupdated Jan 2024Jun 2023granted Dec 2023Jan 2024Moray2.1
Loanhead Farmbattery storagebattery storage49.9application submittedupdated Jun 2025May 2025—Jun 2025Moray3.3
Hill of Towie (Drummuir)wind farmwind farm48operationalupdated Jun 2020Nov 2002granted Nov 2003Jun 2020Moray3.4
Hill of Towie II Wind Farmwind farmwind farm48permission expiredupdated Jun 2020Oct 2013granted Jun 2017Jun 2020Moray3.4
Milltown Airfield (Speyslaw)solar farmsolar farm50approved, not built may be out of dateupdated Sep 2020Jul 2017granted May 2018Sep 2020Moray5.8
RAF Lossiemouthsolar farmsolar farm5application submittedupdated Jul 2026May 2026—Jul 2026Moray6.5
Speyslaw Farmbattery storagebattery storage19.9approved, not built may be out of dateupdated Mar 2023Dec 2021granted Feb 2023Mar 2023Moray8.1
Speyslaw Solar Farmsolar farmsolar farm20approved, not built may be out of dateupdated Sep 2020May 2017granted Aug 2017Sep 2020Moray8.2
Blackhills Wind Farmwind farmwind farm43.2application submittedupdated Oct 2025Aug 2025—Oct 2025Moray8.4
Blackhills Wind Farmbattery storagebattery storage20application submittedupdated Oct 2025Aug 2025—Oct 2025Moray8.4
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Scottish Water Treatment Plant, Moycroft Roadrooftop solarrooftop solar—application submittedupdated May 2026Apr 2026—May 2026Moray2.0

Distance from the average position of the IV30 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm3120075
Rooftop solar110000
Wind farm3101043.2
Battery storage42200120

MW in pipeline: pending, approved and under-construction capacity.

How Moray decides solar, wind and battery applications

ApplicationsMorayUK
Decided applications (solar, wind, battery)2110,236
Refused7 (33%)19%
Solar refused0 of 212%
Onshore wind refused7 of 1445%
Battery storage refused0 of 516%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed4 / 6—

All projects in Moray

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near IV30, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.