Energy Projects Near You

Solar, wind and battery projects near Buckie (AB56)

4 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of AB56 (Moray): 1 approved but not yet running, 2 operational. The largest live scheme is Lurg Hill Wind Farm (15 MW wind farm, approved on 25 February 2019, not yet built; REPD status may be out of date), 9.3 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Moray East (950 MW, operational), 33.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

4projects within 10 km
0awaiting a decision
1approved, not running
2operational

Projects within 10 km of AB56

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Netherton of Windyhillswind farmwind farm4.6operationalupdated Mar 2015Jun 2009granted Oct 2010Mar 2015Moray9.1
Lurg Hill Wind Farmwind farmwind farm15approved, not built may be out of dateupdated Sep 2019Sep 2017granted Feb 2019Sep 2019Moray9.3
Netherton Of Windyhills (extension)wind turbinewind turbine2.3refusedupdated Apr 2014Oct 2012refused Feb 2014Apr 2014Moray9.7
Myreton Crossroadswind farmwind farm1.6operationalupdated Sep 2013Feb 2009granted Jul 2010Sep 2013Moray9.8

Distance from the average position of the AB56 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm3012015
Wind turbine100010

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Moray East950operationalupdated Apr 202333.6

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Moray decides solar, wind and battery applications

ApplicationsMorayUK
Decided applications (solar, wind, battery)2110,236
Refused7 (33%)19%
Solar refused0 of 212%
Onshore wind refused7 of 1445%
Battery storage refused0 of 516%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed4 / 6—

All projects in Moray

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near AB56, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.