Consent for Moray East came in spring 2014, and construction began more than five years later. The application was submitted on 28 August 2012, and Scottish Ministers granted consent under Section 36 on 19 March 2014, after 81 weeks, almost exactly the median for such decisions (81.1). Work started on 6 June 2019, and the 100 turbines of 9.5 MW, each 204 m tall, have been operational since 1 April 2022. The farm holds a Contract for Difference from the AR2 round. The data give no reason for the pause.
How it differs from Beatrice and Moray West
Beatrice, 16.4 km away, received its consent the same day, but has been operational since 5 August 2019, almost three years earlier; it has 588 MW and 7 MW turbines. Moray West, at 882 MW, comes fifth in the list of operational farms, straight after Moray East, which is fourth of 49 in the REPD extract for July 2026. The nearest districts on land: Buckie, Banff and Macduff.