Moray West offshore wind farm

Moray West Offshore Wind Farm Project is an 882 MW offshore wind farm with 60 turbines in Scottish waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 April 2025; the record was last updated on 14 May 2026. Its REPD grid reference is 17 km from the nearest postcode on land (KW7 6HB, Highland). As an offshore wind farm in Scottish waters, it is consented by Scottish Ministers; REPD names Marine Scotland as the consenting authority.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

882 MWoffshore wind farm
operationalstatus in REPD
14 May 2026record last updated
17 km from land (Highland)REPD location

Consent timeline

DateStage
5 July 2018Application submitted
14 June 2019Marine licence and Section 36 consent granted (Scottish Ministers)
1 May 2022Construction started
1 April 2025Operational

Project details

Technology
offshore wind farm
Capacity
882 MW
Turbines
60
Turbine capacity
14.7 MW
Turbine height
230 m
Status (REPD)
operational
Record last updated
14 May 2026
Operator or applicant
EDPR
Consenting authority (REPD)
Marine Scotland
Application reference
not recorded
Nearest postcode on land
KW7 6HB (Highland), 16.6 km from the REPD grid reference
Time to decision
49 weeks
Contracts for Difference
AR6
REPD reference
6158

Who decides

As an offshore wind farm in Scottish waters, it is consented by Scottish Ministers; REPD names Marine Scotland as the consenting authority.

Postcode districts within 40 km

Districtkm
Berriedale (KW7)17.1
East Helmsdale (KW8)21.3
Dunbeath (KW6)21.5
Latheronwheel (KW5)24.5
Lybster (KW3)26.4
Whaligoe (KW2)32.2
Brora (KW9)32.7
Lossiemouth (IV31)39.3

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Beatrice588operational21.4

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (58.0699, -3.3131).