Energy Projects Near You

Solar, wind and battery projects near Brora (KW9)

4 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KW9 (Highland): 2 operational. The largest scheme is Gordonbush (70 MW wind farm, operational since 12 June 2012), 7.8 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Moray West Offshore Wind Farm Project (882 MW, operational), 32.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

4projects within 10 km
0awaiting a decision
0approved, not running
2operational

Projects within 10 km of KW9

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Kintradwell Lodge Wind Farmwind farmwind farm63refusedupdated Nov 2023Feb 2021refused Nov 2023Nov 2023Highland7.1
Kilbraur Windfarm Farlary - Extensionwind farmwind farm20operationalupdated Oct 2011Mar 2009granted Dec 2009Oct 2011Highland7.4
Gordonbushwind farmwind farm70operationalupdated Jul 2012Jun 2003granted Apr 2008Jul 2012Highland7.8
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Kintradwell Lodge Wind Farm & Battery storagebattery storagebattery storage—refusedupdated Nov 2023Feb 2021refused Nov 2023Nov 2023Highland7.1

Distance from the average position of the KW9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm300210
Battery storage100010

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Moray West Offshore Wind Farm Project882operationalupdated May 202632.7

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.