Energy Projects Near You

Gordonbush (70 MW wind farm)

Gordonbush is a 70 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 12 June 2012; the record was last updated on 4 July 2012. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

70 MWwind farm
operationalstatus in REPD
4 July 2012record last updated
Highlandcouncil area

Planning timeline

DateStage
17 June 2003Application submitted
9 April 2008Section 36 consent granted (Scottish Ministers)
1 July 2010Construction started
12 June 2012Operational

Project details

Technology
wind farm
Capacity
70 MW
Status (REPD)
operational
Record last updated
4 July 2012
Operator or applicant
Scottish and Southern Energy (SSE)
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Turbines
35
Address (REPD)
Gordonbush Estate, Brora, Sutherland, Highlands
Council area (by location)
Highland
Time to decision
251 weeks
REPD reference
3662

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Gordonbush (extension)wind farm47operational3.2
Balnacoil Wind Farmwind farm45refused4.3
Kilbraur Windfarmwind farm47.5operational6.2
South Kilbraur Wind Farmwind farm28refused6.6
Kintradwell Lodge Wind Farmwind farm63refused7.2
Kilbraur Windfarm Farlary - Extensionwind farm20operational7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.0595, -3.9591).