Energy Projects Near You

Kilbraur Windfarm (47.5 MW)

Kilbraur Windfarm is a 47.5 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 14 June 2008; the record was last updated on 23 October 2009.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

47.5 MWwind farm
operationalstatus in REPD
23 October 2009record last updated
Highlandcouncil area

Planning timeline

DateStage
4 September 2003Application submitted
1 April 2006Planning permission granted
1 September 2007Construction started
14 June 2008Operational

Project details

Technology
wind farm
Capacity
47.5 MW
Status (REPD)
operational
Record last updated
23 October 2009
Operator or applicant
Renewable Development Company (RDC)
Planning authority
Highland
Planning application reference
SU2004125
Turbines
19
Address (REPD)
Rogart, Sutherland (former Strath Brora Site)
Council area (by location)
Highland
Time to decision
134 weeks
REPD reference
3202

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
South Kilbraur Wind Farmwind farm28refused0.6
Balnacoil Wind Farmwind farm45refused4.3
Gordonbushwind farm70operational6.2
Tressady Wind Farmwind farm32.5refused on appeal6.9
Kilbraur Windfarm Farlary - Extensionwind farm20operational7.1
Strathborawind farm46application withdrawn7.3
Gordonbush (extension)wind farm47operational7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.0404, -4.0588).