Energy Projects Near You

Solar, wind and battery projects near Golspie (KW10)

4 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KW10 (Highland): 3 operational. The largest scheme is Gordonbush (70 MW wind farm, operational since 12 June 2012), 9.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

4projects within 10 km
0awaiting a decision
0approved, not running
3operational

Projects within 10 km of KW10

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Kilbraur Windfarm Farlary - Extensionwind farmwind farm20operationalupdated Oct 2011Mar 2009granted Dec 2009Oct 2011Highland2.0
South Kilbraur Wind Farmwind farmwind farm28refusedupdated Sep 2020Nov 2019refused Sep 2020Sep 2020Highland8.4
Kilbraur Windfarmwind farmwind farm47.5operationalupdated Oct 2009Sep 2003granted Apr 2006Oct 2009Highland8.7
Gordonbushwind farmwind farm70operationalupdated Jul 2012Jun 2003granted Apr 2008Jul 2012Highland9.5

Distance from the average position of the KW10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm400310

MW in pipeline: pending, approved and under-construction capacity.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.