Energy Projects Near You

Solar, wind and battery projects near Pittentrail (IV28)

4 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IV28 (Highland): 1 operational. The largest scheme is Kilbraur Windfarm (47.5 MW wind farm, operational since 14 June 2008), 6.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

4projects within 10 km
0awaiting a decision
0approved, not running
1operational

Projects within 10 km of IV28

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Tressady Wind Farmwind farmwind farm32.5refused on appealupdated Sep 2014Jul 2013refused Feb 2014Sep 2014Highland4.2
South Kilbraur Wind Farmwind farmwind farm28refusedupdated Sep 2020Nov 2019refused Sep 2020Sep 2020Highland6.4
Kilbraur Windfarmwind farmwind farm47.5operationalupdated Oct 2009Sep 2003granted Apr 2006Oct 2009Highland6.8
Strathborawind farmwind farm46application withdrawnupdated May 2009Jun 2009—May 2009Highland6.8

Distance from the average position of the IV28 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm400120

MW in pipeline: pending, approved and under-construction capacity.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.