South Kilbraur Wind Farm (28 MW)

South Kilbraur Wind Farm is a 28 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 4 September 2020; the record was last updated on 30 September 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

28 MWwind farm
refusedstatus in REPD
30 September 2020record last updated
Highlandcouncil area

Planning timeline

DateStage
23 November 2019Application submitted
4 September 2020Refused by the planning authority

Project details

Technology
wind farm
Capacity
28 MW
Status (REPD)
refused
Record last updated
30 September 2020
Operator or applicant
Wind 2
Planning authority
Highland
Planning application reference
19/04826/FUL
Turbines
7
Turbine height
150 m
Address (REPD)
Land 1700M South Of, 43 Farlary, Rogart, Highlands
Council area (by location)
Highland
Time to decision
41 weeks
REPD reference
6821

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kilbraur Windfarmwind farm47.5operational0.6
Balnacoil Wind Farmwind farm45refused4.8
Gordonbushwind farm70operational6.6
Tressady Wind Farmwind farm32.5refused on appeal6.8
Kilbraur Windfarm Farlary - Extensionwind farm20operational6.9
Strathborawind farm46application withdrawn7.4
Gordonbush (extension)wind farm47operational8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.0357, -4.0617).