Gordonbush (extension) (47 MW wind farm)

Gordonbush (extension) is a 47 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 January 2021; the record was last updated on 16 January 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

47 MWwind farm
operationalstatus in REPD
16 January 2026record last updated
Highlandcouncil area

Planning timeline

DateStage
1 June 2015Application submitted
29 September 2017Section 36 consent granted (Scottish Ministers)
1 May 2020Construction started
1 January 2021Operational

Project details

Technology
wind farm
Capacity
47 MW
Status (REPD)
operational
Record last updated
16 January 2026
Operator or applicant
Scottish and Southern Energy (SSE)
Planning authority
Scottish Government (S36)
Planning application reference
EC00003105
Turbines
11
Turbine height
150 m
Address (REPD)
near Brora in Sutherland.
Council area (by location)
Highland
Time to decision
122 weeks
REPD reference
3435

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Gordonbushwind farm70operational3.2
Balnacoil Wind Farmwind farm45refused4.2
Kintradwell Lodge Wind Farmwind farm63refused7.1
Kilbraur Windfarmwind farm47.5operational7.9
South Kilbraur Wind Farmwind farm28refused8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.0882, -3.9589).