Strathbora (46 MW wind farm)
Strathbora is a 46 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 6 May 2009; the record was last updated on 6 May 2009.
46 MWwind farm
application withdrawnstatus in REPD
6 May 2009record last updated
Highlandcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 6 May 2009 | Application withdrawn |
| 12 June 2009 | Application submitted |
Project details
- Technology
- wind farm
- Capacity
- 46 MW
- Status (REPD)
- application withdrawn
- Record last updated
- 6 May 2009
- Operator or applicant
- Renewable Development Company (RDC)
- Planning authority
- Highland
- Planning application reference
- SU2003332
- Turbines
- 19
- Address (REPD)
- Strath Brora Rogart Sutherland
- Council area (by location)
- Highland
- REPD reference
- 3183
Who decides
| Applications | Highland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 160 | 10,236 |
| Refused | 68 (42%) | 19% |
| Solar refused | 0 of 15 | 12% |
| Onshore wind refused | 61 of 114 | 45% |
| Battery storage refused | 7 of 31 | 16% |
| Median time from submission to decision | 52.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 20 / 20 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Tressady Wind Farm | wind farm | 32.5 | refused on appeal | 2.8 |
| Kilbraur Windfarm | wind farm | 47.5 | operational | 7.3 |
| South Kilbraur Wind Farm | wind farm | 28 | refused | 7.4 |
| Balnacoil Wind Farm | wind farm | 45 | refused | 8.5 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.0705, -4.1699).