Tressady Wind Farm (32.5 MW)
Tressady Wind Farm is a 32.5 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 6 August 2014; the record was last updated on 2 September 2014.
32.5 MWwind farm
refused on appealstatus in REPD
2 September 2014record last updated
Highlandcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 22 July 2013 | Application submitted |
| 25 February 2014 | Refused by the planning authority |
| 6 August 2014 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 32.5 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 2 September 2014
- Operator or applicant
- Wind Prospect Developments
- Planning authority
- Highland
- Planning application reference
- 13/02749/FUL
- Appeal reference
- 14/00009/REFSU
- Turbines
- 13
- Address (REPD)
- 5km north of Rogart and 2km west of Rilochan
- Council area (by location)
- Highland
- Time to decision
- 31 weeks
- REPD reference
- 4421
Who decides
| Applications | Highland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 160 | 10,236 |
| Refused | 68 (42%) | 19% |
| Solar refused | 0 of 15 | 12% |
| Onshore wind refused | 61 of 114 | 45% |
| Battery storage refused | 7 of 31 | 16% |
| Median time from submission to decision | 52.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 20 / 20 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Strathbora | wind farm | 46 | application withdrawn | 2.8 |
| South Kilbraur Wind Farm | wind farm | 28 | refused | 6.8 |
| Kilbraur Windfarm | wind farm | 47.5 | operational | 6.9 |
| Balnacoil Wind Farm | wind farm | 45 | refused | 9.4 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.0457, -4.1762).