Energy Projects Near You

Tressady Wind Farm (32.5 MW)

Tressady Wind Farm is a 32.5 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 6 August 2014; the record was last updated on 2 September 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

32.5 MWwind farm
refused on appealstatus in REPD
2 September 2014record last updated
Highlandcouncil area

Planning timeline

DateStage
22 July 2013Application submitted
25 February 2014Refused by the planning authority
6 August 2014Appeal refused

Project details

Technology
wind farm
Capacity
32.5 MW
Status (REPD)
refused on appeal
Record last updated
2 September 2014
Operator or applicant
Wind Prospect Developments
Planning authority
Highland
Planning application reference
13/02749/FUL
Appeal reference
14/00009/REFSU
Turbines
13
Address (REPD)
5km north of Rogart and 2km west of Rilochan
Council area (by location)
Highland
Time to decision
31 weeks
REPD reference
4421

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Strathborawind farm46application withdrawn2.8
South Kilbraur Wind Farmwind farm28refused6.8
Kilbraur Windfarmwind farm47.5operational6.9
Balnacoil Wind Farmwind farm45refused9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.0457, -4.1762).