Energy Projects Near You

Solar, wind and battery projects near Balintore (IV20)

2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IV20 (Highland): none of them is pending, approved or operational. The largest scheme is Nigg Hill (10 MW wind farm, refused on 28 January 2013), 7.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2projects within 10 km
0awaiting a decision
0approved, not running
0operational

Projects within 10 km of IV20

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hill of Niggwind farmwind farm7.5refusedupdated Jul 2015Jan 2015refused Jun 2015Jul 2015Highland7.4
Nigg Hillwind farmwind farm10refusedupdated May 2013Jan 2008refused Jan 2013May 2013Highland7.5

Distance from the average position of the IV20 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm200020

MW in pipeline: pending, approved and under-construction capacity.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.