Energy Projects Near You

Solar, wind and battery projects near Alness (IV17)

12 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IV17 (Highland): 2 are waiting for a planning decision, 5 approved but not yet running, 3 operational. The largest live scheme is Drumore Cottage, Swordale (49.9 MW battery storage, approved on 10 December 2024, not yet built), 9.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12projects within 10 km
2awaiting a decision
5approved, not running
3operational

Projects within 10 km of IV17

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Smithybattery storagebattery storage45approved, not builtupdated Mar 2025Jan 2024granted Jan 2025Mar 2025Highland1.6
Strathrory Wind Farmwind farmwind farm36approved, not builtupdated Mar 2023Mar 2020granted Jan 2022Mar 2023Highland7.7
Torr Leathann, Ardross Wind Farmwind farmwind farm36refusedupdated Jun 2022Jun 2022refused Nov 2022Jun 2022Highland8.0
Torr Leathann, Ardrossbattery storagebattery storage5refusedupdated Jun 2022Jun 2022refused Nov 2022Jun 2022Highland8.0
Drumore Cottage, Swordalebattery storagebattery storage49.9approved, not builtupdated Jan 2025Jun 2023granted Dec 2024Jan 2025Highland9.0
Beinn Tharsuinn Extension (Beinn nan Oighrean)wind farmwind farm4.6operationalupdated Apr 2018Jan 2007granted Dec 2008Apr 2018Highland10.0
Bendealt Wind Farm, Highlandwind farmwind farm9operationalupdated Apr 2011May 1995granted Aug 1996Apr 2011Highland10.0
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Alness Academysolar farmsolar farm0.5under constructionupdated Feb 2020Jan 2019granted Mar 2019Feb 2020Highland0.7
Creachan Wind Farm & BESSwind farmwind farm—application submittedupdated Apr 2026Feb 2026—Apr 2026Highland0.8
Creachan Wind Farm & BESSbattery storagebattery storage—application submittedupdated Apr 2026Feb 2026—Apr 2026Highland0.8
Invergordon Academysolar farmsolar farm0.2operationalupdated Nov 2019Jan 2019granted Feb 2019Nov 2019Highland5.5
Strathrory Wind Farmbattery storagebattery storage—approved, not builtupdated Mar 2023Mar 2020granted Jan 2022Mar 2023Highland8.0

Distance from the average position of the IV17 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm201100.5
Wind farm5112136
Battery storage5130194.9

MW in pipeline: pending, approved and under-construction capacity.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.