Energy Projects Near You

Solar, wind and battery projects near Dingwall (IV15)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IV15 (Highland): 2 are waiting for a planning decision, 1 approved but not yet running. The largest live scheme is Ceislein Wind Farm (77 MW wind farm, application submitted on 13 March 2026, no decision recorded), 0.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
2awaiting a decision
1approved, not running
0operational

Projects within 10 km of IV15

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ceislein Wind Farmwind farmwind farm77application submittedupdated Apr 2026Mar 2026—Apr 2026Highland0.5
Ceislein Wind Farmbattery storagebattery storage65application submittedupdated Apr 2026Mar 2026—Apr 2026Highland0.5
Woodlands Wind Farmwind farmwind farm15application withdrawnupdated Dec 2014Dec 2013—Dec 2014Highland3.1
Drumore Cottage, Swordalebattery storagebattery storage49.9approved, not builtupdated Jan 2025Jun 2023granted Dec 2024Jan 2025Highland7.0
Clach Liath Wind Farmwind farmwind farm42.5refusedupdated Feb 2013Apr 2012refused Feb 2013Feb 2013—8.8
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Swordale Wind turbinewind turbinewind turbine0.6refusedupdated Oct 2021Mar 2021refused Sep 2021Oct 2021Highland0.5
Knockbain Farmwind turbinewind turbine—refusedupdated Jun 2025Oct 2024refused May 2025Jun 2025Highland1.5
Somerby Farm, Lochussiewind turbinewind turbine0.4refusedupdated Jul 2024Jan 2024refused May 2024Jul 2024Highland3.3

Distance from the average position of the IV15 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm3100177
Wind turbine300030
Battery storage21100115

MW in pipeline: pending, approved and under-construction capacity.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.