Clach Liath Wind Farm (42.5 MW)

Clach Liath Wind Farm is a 42.5 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 13 February 2013; the record was last updated on 26 February 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

42.5 MWwind farm
refusedstatus in REPD
26 February 2013record last updated
Scotlandcouncil area

Planning timeline

DateStage
30 April 2012Application submitted
13 February 2013Refused by the planning authority

Project details

Technology
wind farm
Capacity
42.5 MW
Status (REPD)
refused
Record last updated
26 February 2013
Operator or applicant
Falck Renewables Wind Ltd
Planning authority
Highland
Planning application reference
12/01689/FUL
Turbines
17
Address (REPD)
Land To The East Of Meall Na Speireig Clach Liath Evanton Ross-shire
Council area (by location)
not known
Time to decision
41 weeks
REPD reference
3853

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bendealt Wind Farm, Highlandwind farm9operational5.5
Meall an Tuirc Wind Farmwind farm17operational5.8
Novar Wind Farm (Extension)wind farm36.8operational5.8
Kirkan Wind Farmwind farm81.6approved, not built5.9
Drumore Cottage, Swordalebattery storage49.9approved, not built6.2
Woodlands Wind Farmwind farm15application withdrawn7.2
Ceislein Wind Farmbattery storage65application submitted9.2
Ceislein Wind Farmwind farm77application submitted9.2
Carn Gorm Wind Farmwind farm42refused on appeal9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.671, -4.4922).